Deliverable

2 min Updated 27.07.2026
In short

A deliverable is an output that has to be produced at a defined point in the project and submitted to the Commission: a report, a dataset, a prototype, a data management plan. It is numbered as “work package number.deliverable number” and has a type and a dissemination level.

Numbering
“WP.number”, e.g. 4.2
Types
R · DEM · DEC · DATA · DMP · ETHICS · SECURITY · OTHER
PU deliverables
Published on CORDIS automatically
Changing the date
No amendment needed

A deliverable is what you submit. The official definition: a report produced at a given moment in the action and submitted to the Commission so the project can be monitored effectively.

The key difference from a milestone: a deliverable is submitted, a milestone is verified.

Numbering and dates

The scheme is strict: work package number, dot, sequence number within that package. So 4.2 is the second deliverable of work package 4. Deliverables are numbered in order of delivery date, and dates are given in months from the project start, where the first month is month 1.

Types

R – document or report (excluding periodic and final reports). DEM – demonstrator, pilot, prototype, plan designs. DEC – websites, patent filings, press and media actions, videos. DATA – data sets. DMP – data management plan. ETHICS and SECURITY – deliverables on those issues. OTHER – software, algorithms, models.

Dissemination level

PU – public. An important detail: deliverables flagged public are automatically published on the project's CORDIS page. "Public" here means genuinely public, not "we do not object".

SEN – sensitive, limited under the conditions of the grant agreement. Then three EU classification levels: R-UE/EU-R, C-UE/EU-C and S-UE/EU-S.

Two mandatory deliverables

Within the first six months you must submit two distinct deliverables: a data management plan and a plan for dissemination and exploitation including communication activities. The data management plan is then updated during the project.

Why not to list extras

The guidance advises including only deliverables essential for effective monitoring, and the reason is practical: each one in Annex 1 is a legal obligation, and removing it later needs an amendment.

A useful asymmetry: adding or removing a deliverable requires an amendment; changing its due date does not.

Frequently asked questions

How does a deliverable differ from a milestone?

A deliverable is submitted to the Commission: it is an artefact you upload to the portal. A milestone is not submitted; it is verified, and the proposal has to state the means of verification for it. A milestone can coincide with the completion of a key deliverable, but they are different things.

We are running late with a deliverable. Do we need an amendment?

No. Changing the due date of a deliverable usually does not require an amendment. Adding or removing the deliverable itself does.

Can a deliverable be made non-public?

Yes, there is the SEN level with restrictions set out in the agreement, and three levels of EU classified information. But remember: everything marked PU is published on CORDIS automatically.

Official materials

Read on GetGrant

Sources

  1. Application form HE RIA/IA V5.1 ec.europa.eu · checked 27.07.2026
  2. Annotated Grant Agreement V2.0 ec.europa.eu · checked 27.07.2026

Data current as of 27.07.2026. Verify the terms with the donor’s official portal before applying.

Updated 27.07.2026 · Reviewed by: GetGrant editorial team

← All terms